top of page
Devastating Fire Destroys Processing Plant
June 14th, 2017
On the evening of June 14th, 2017 a fire broke out in our processing plant. Thanks to the gallant efforts of the local fire department, no animals, people or other structures were lost.

The Rebuild Process

Rebuild 2018
Early 2018 we broke ground on the new processing plant. With new space and new equipment we look forward to serving customers again soon.

Reopen Date
Progress is going well and on target. Estimated to reopen Fall 2018.

Revised Completion
After the latest meeting with the trades and engineers we have confirmed completion of the facility for early 2019.
Processing Plant Now
June 2024
Current day our new processing plant has been in operation since 2019 and continues to provide Kamloops and the surrounding communities with a variety of high quality dairy products.

bottom of page